Library Renovation Look Ahead: Week of June 6

As we move ahead in the Library Renovation Project, we will keep you up to date on construction activity.

June 6-7: Consigli will be finishing up installing the windows on Ward St.

June 6-10: Consigli will be continue to demo and install the windows on the Pike side of Beatty Hall.

Interior wise, Consigli will begin working on installing lights, and will continue to work on installing the sprinkler heads and drops, and the acoustic wood ceilings panels during the next couple of weeks.