Thanks to the generous donation of WIT Alumnus Faisal Al Shawaf, a rooftop terrace will be constructed above the Flannagan Campus Center Pavillion in Beatty Hall!
During this time, the Bill & Jean Whelan Cafe and Reading Lounge will be inaccessible during the entire run of the interior construction. There will be some noise and disruption throughout the process. Earplugs will be available at the service desks for your convenience.
Current issues of periodicals have been temporarily relocated to the periodical stacks on the Mezzanine Level.
Construction Schedule
- July 29 – July 31: Set up a temporary partition
- July 31 – August 5: Remove millwork for storefronts (removing windows)
- August 6 – August 12: Mechanical piping modifications (relocating pipes)
- August 13 – August 16: Storefront modifications
Contact Physical Plant at (617) 989-4555 for additional information.