Library Renovation Look Ahead: Week of May 16

This Saturday, May 14th, from 6AM to 4PM, Consigli will be using a crane to deliver and position steel on the roof of Beatty Hall. Public Safety will be on site and signage will be placed to guide pedestrians around these areas.  Parking in the West Lot will be limited as a result, and it is requested that you park at the Parker St. Lot if you are visiting campus.

From there, Consigli will be working on installing the AHU roof dunnage, and the demolition and installation of the windows on the south façade during the week of May 16th.